Bouygues Energies & Services enlisted 200 employees - of which 90% were local and trained as network engineers - to supply the Gabonese Ministry of Energy with a range of turnkey solutions including financing, design, construction of an “energy boulevard” (high and low-voltage networks), rural electrification and street lighting.

100

km of power lines

€32

million invested

200

workers involved in the project

Our service

For the same investment, Bouygues Energies & Services also installed ‘dark fibre’ along the 100km of high-voltage line (dark fibre is essentially optical fibre infrastructure that is not in use).

Thanks to its expertise in digital development, the subsidiary Axione was able to create a digital backbone that will make it possible to connect inhabitants much more quickly and act as a further stimulus to economic development.

Bouygues Energies & Services already has a large footprint in Africa, with three well-established subsidiaries in Congo, Gabon and Ivory Coast, 1,300 employees (only around 10 of which are expatriates) and involvement in technically complex, high-value-added projects in other countries.

Our latest case studies

0 1 2 3 4 5

Latest news

Find all the topics that make Bouygues Energies & Services news: projects, innovations, public and client events, partnerships, press releases ...

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45